Follow the Job
Here we aim to show you the progress of our work day by day during our working year – similar to a Diary.
Obviously this will depend on our project at the time which can vary greatly from a small pathway taking just one day to a complete garden landscape which can take weeks.
We hope you will find it informative:-
Project of the Week
Job Description
To supply and lay Brett Omega Driveway in Autumn Gold
Day One
To dig out existing tarmac drive
Day Two
To install the stone sub base and compact using a compactor plate.
Day Three
To install a charcoal edging and to screed out the grit sand.
Day Four
The blocks are delivered to site and laying has begun in a 90 degree herringbone design.
Day Five
Job finished. The blocks have been laid and the drive compacted, kiln dried sand brushed into the joints and finally compacted again.